| Conduit Manufacturer, Northern Illinois
Mr. Smith was Project Manager for the investigation and remediation
of a 16-acre site purchased by the client. The site was first occupied
in 1918, but was abandoned at the time of the site investigation, which
detected elevated concentrations of lead in the soils throughout the site,
as well as lead concentrations in groundwater above potable use standards.
Within one month of initial contact with the Illinois Environmental Protection
Agency (IEPA), a redesignation of the groundwater was negotiated, allowing
the purchase to proceed. Site specific soil cleanup objectives calculated
using IEPA approved methodology were approved by the IEPA. Remediation
activities included the excavation and disposal of more than 15,000 cubic
yards of soil, removal of four (4) USTs and abatement of greater than
100,000 square feet of asbestos containing material.
Following the excavation of the impacted soil, various grades of backfill
were used to prepare road subbases capable of supporting heavy truck traffic.
In areas not to be used for future roads, the backfill was placed to maintain
a level grade over a 300-foot distance. The site remediation activities
were conducted concurrently with the complete renovation of a 330,000
square foot building on the site and were completed in less than four
(4) months. This necessitated close coordination and frequent meetings
with the contractors not associated with the remediation activities.
School District, Northern Illinois
Mr. Smith was Project Manager for the remediation of a LUST site located
at a high school in Northern Illinois. Mr. Smith oversaw the design, construction,
and operation of a sequenced series of aerated biopiles. Given the limited
available space, five (5) individual biopiles were constructed only after
each previous biopile had been remediated and the soil returned to the
excavation.
Steel Manufacturer, Northern Illinois
Mr. Smith was Project Manager for the preparation of a Corrective Measures
Study under RCRA for the remediation of groundwater contaminated with
chlorinated solvents. The project consisted of installing and running
pump tests on nested monitoring wells, modeling groundwater flow direction
and velocity, evaluating a variety of potential remediation technologies,
and performing a risk assessment. The Corrective Measures Study followed
the requirements of USEPA's guidance documents. This was one of the first
Corrective Measures Studies in Region 5 and Mr. Smith worked closely with
USEPA to insure the agency's concerns were addressed prior to the client
undertaking a major phase of the project. During the evaluation of alternatives,
it was demonstrated that: given the client owned all of the property between
the landfill and the river and this land would remain industrial property
and the installation of potable groundwater wells in this area would be
prohibited, groundwater treatment was not required.
The risk assessment demonstrated that the discharge of impacted groundwater
to the river would not pose an adverse human health risk. Based on this
risk assessment, a limited action alternative involving continued groundwater
monitoring was approved by the U.S. EPA, but no other equipment installation
was required.
CFB Cogeneration Facility, Northern West Virginia
Mr. Smith was Project Manager for the remediation of greater than 25,000
cubic yards of soil contaminated with heavy metals from an abandoned glass
manufacturing building. Remediation activities included: soil excavation,
treatment, stockpiling, and placement on-site. The treated soil was used
to raise the overall elevation of the site. The construction schedule
for the cogeneration facility required that parcels of the site undergo
partial closure rather than closure of the entire site as a whole.
Gas Station, Central Wisconsin
Mr. Smith designed soil vapor extraction system for site contaminated
with gasoline products. Project included evaluation of remediation alternatives,
communication with the client, and design of soil vapor extraction system.
Underground Storage Tank Investigation and Remediation at a Heating
Plant, Chicago, Illinois
Mr. Green prepared a three-dimensional computer model of the site facilities
demonstrating the presence of a third source of PNAs/PAHs in the soil,
of an undetermined origin, that was physically separate from the five
(5) regulated 20,000-gallon underground heating oil storage tanks. This
sophisticated modeling was necessary as the tank impacted soil, the cinder
fill material and the third source of an undetermined origin, all contained
PNAs/PAHs, although in somewhat different concentrations. Mr. Green left
the soil impacted by an undetermined source in place, then managed the
cinder fill material as a separate waste distinct from the soil impacted
by the release from the 20,000-gallon heating oil storage tank, saving
the client greater than $1 million in remediation costs.
Mr. Green provided field management during the removal of five (5) 20,000-gallon
underground storage tanks and the excavation, transportation and disposal
in a permitted landfill, of approximately 3,000 cubic yards of soil impacted
with PNAs/PAHs. Mr. Green also managed the design, installation and operation
of a groundwater pump and treatment system, and coordinated its operation
with the design, installation and operation of the site de-watering system.
Closure sampling, designed and managed by Mr. Green, demonstrated that
the impacted soil and groundwater were successfully removed. Mr. Green
also provided field management during the installation of three (3) 35,000-gallon
underground storage tanks.
Mr. Green prepared a Corrective Action Completion Report that was approved
by the Illinois EPA. This report contained three-dimensional modeling
of the site to differentiate the soils impacted by the UST release from
the release of undetermined origin, and also from site fill material that
contained cinders and building materials from the early 20th century.
RCRA Investigation and Remediation, Northeast Illinois
Mr. Green prepared a RCRA Closure Plan that successfully demonstrated
the efficacy of microorganisms to remediate approximately 5,000 cubic
yards of soil impacted with chlorinated solvents, without leaving vinyl
chloride as an end product. Upon completion of the bioremediation, performed
by a subcontractor, Mr. Green collected soil and groundwater closure samples
demonstrating that the constituents of concern were remediated to concentrations
below their respective clean-up objectives. In the final phase of the
project, Mr. Green prepared a RCRA Closure Documentation Report that was
approved by the IEPA.
Investigation, Underground Tank Removal and Risk-Based Remediation
of Chlorinated Solvents, Indianapolis, Indiana
Mr. Green designed and performed subsurface investigations to assess
the extent of soil and groundwater impacted with solvents associated with
a leaking underground tank at a printing press service facility located
in Indianapolis, Indiana. The investigations included drilling 21 soil
borings and the installation and sampling of six (6) groundwater monitoring
wells as deep as 200-feet. Mr. Green managed the removal, cleaning and
disposal of the leaking underground tank and its contents.
Risk-Based Closure activities performed by Mr. Green include fate and
transport modeling of two (2) chemicals of concern using Visual MODFLOWâ,
MT3D®, and AutoCADD 14â. The fate & transport modeling performed
by Mr. Green demonstrated that plumes of the chemicals of concern in groundwater
would stabilize within 100-years, and would not migrate off-site or down
to the usable aquifer within 1,000-years. This modeling effort enabled
the client to proceed with a risk-based site closure, saving more than
20% compared to proposed active treatment options.
next page ...
|